. THE WILLOW .

September 13th, 2019. Rezoning Approved!

We will submit the Development Permit package drawings very shortly!

Rezoning Done.jpg

. THE WILLOW .

August 27th, 2019. City’s Public Hearing is scheduled for September 12th. Things are moving fast now!

Public Hearing.jpg

. HEATHER AND SEVENTEENTH .

August 22nd, 2019. Third floor slab done!


. WEST 28th & ASH .

August 10th, 2019. NEW PROJECT: We are so excited about this one: Just acquired the land to build 16 Luxury townhome units on the corner of West 28th and Ash, the highest elevation point in the area, WITH FABULOUS DOWNTOWN AND NORTH SHORE MOUNTAIN VIEWS! Design phase will commence soon!


. HEATHER AND SEVENTEENTH .

August 2nd, 2019. Second floor slab done!

Second floor 2.jpeg

. BRITISH PROPERTIES RESIDENCE .

April 4th, 2019. Pool season draws near! Click HERE for a new video of our project. We love this house!


. THE WILLOW .

April 3rd, 2019. SHAPE Architecture and Terra Blanka will be meeting with the City of Vancouver next week to discuss the final details of rezoning for the project.

. HEATHER AND SEVENTEENTH .

April 3rd, 2019. Urban One Builders has commenced pouring the P1 suspended slab. Things are moving along quickly!

IMG_1006.PNG

. HEATHER AND SEVENTEENTH .

March 27th, 2019. Getting ready to pour the P2 slab on grade.

IMG_0653.PNG